Bronx and Queens Reforestation FY10
-
100% complete
-
100% complete
-
100% complete
This multisite contract will plant new and replacement trees in the Bronx and Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2012
Projected Completion Date:
January 2013
Completion Date:
December 2012
(Design)
Procurement
Start Date: December 2012
Projected Completion Date:
September 2013
Completion
Date:
February 2013
(Procurement)
Construction
Start Date: March 2013
Projected Completion Date:
June 2015
Completion Date: May 2015
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations in the Bronx and Queens.