Brooklyn and Staten Island Reforestation FY14
-
100% complete
-
100% complete
-
100% complete
This multisite contract will remove invasive species and plant new trees in Brooklyn and Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2013
Projected Completion Date:
June 2013
Completion Date:
August 2013
(Design)
Procurement
Start Date: August 2013
Projected Completion Date:
May 2014
Completion
Date:
May 2014
(Procurement)
Construction
Start Date: May 2014
Projected Completion Date:
November 2016
Completion Date: November 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations, Brooklyn and Staten Island
Project Staff
Contact NYC Parks about this project