William Gunn Playground Multipurpose Play Area Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the multipurpose play area at William Gunn Playground.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: March 2025
Projected Completion Date: April 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Detective William T. Gunn Playground, Queens
Near 235th Court between Hillside and 87th Avenue
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project