New York State Pavilion Observation Towers Reconstruction - Phase 1
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date:
April 2018
(Design)
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
July 2019
(Procurement)
Construction
Start Date: October 2019
Projected Completion Date:
April 2021
Completion Date: April 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- State
Location
Flushing Meadows Corona Park, Queens
Perimeter Road and United Nations Avenue South
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower