Zimmerman Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct Zimmerman Playground including play equipment, safety surface, spray shower, basketball courts, fitness equipment, security lighting, site furnishings, pavements, planting, drainage, and utilities.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2022
Projected Completion Date: January 2024
Completion Date: January 2024 (Design)

Procurement

Start Date: January 2024
Projected Completion Date: February 2026
Completion Date: October 2025 (Procurement)

Construction

Start Date: October 2025
Projected Completion Date: October 2026

Understand how we build parks.

Funding

Total Funding: $6,948,000
Funding Sources:
  • City Council
  • Mayoral

Location

Zimmerman Playground, Bronx
Britton Street between Olinville Avenue and Barker Avenue
Community Board: 11

 

Project Staff

Project Liaison: Katerine Borrome