Queens Green Infrastructure Construction (QG-518M)
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water at Helen Marshall Playground, Electric Playground, Horace Harding Playground, London Planetree Playground, and Joseph P. Addabbo Memorial Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2018
Projected Completion Date:
June 2019
Completion Date:
February 2021
(Design)
Procurement
Start Date: February 2021
Projected Completion Date:
November 2021
Completion
Date:
April 2023
(Procurement)
Construction
Start Date: June 2023
Projected Completion Date:
December 2024
Completion Date: September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Electric Playground, Queens
W/S 164 Street, S/O 65 Avenue
Community Board: 08 -
Horace Harding Playground, Queens
62 Drive between 97 Place & 98 Street
Community Board: 06
Project Staff
Contact NYC Parks about this project