Bronx, Manhattan and Queens Reforestation FY18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new and replacement trees in the Bronx, Manhattan and Queens.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: December 2017
Completion Date: January 2018 (Design)

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: October 2018 (Procurement)

Construction

Start Date: November 2018
Projected Completion Date: May 2021
Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $1,052,000
Funding Source: Mayoral

Location

Various locations in the Bronx, Manhattan and Queens

Project Staff

Contact NYC Parks about this project