Marlboro Playground and Cadman Plaza Park Public Restroom Building Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct the public restroom buildings at Marlboro Playground and Cadman Plaza Park.
Project Notes
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2017
Projected Completion Date:
August 2019
Completion Date:
January 2023
(Design)
Procurement
Start Date: January 2023
Projected Completion Date:
September 2021
Adjusted Completion
Date:
August 2025
(Procurement)
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
- State
Locations
-
Cadman Plaza Park, Brooklyn
Tillary, Cadman Plaza East, Prospect Streets
Community Board: 02 -
Marlboro Playground, Brooklyn
West 11th Street & Avenue W
Community Board: 13
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project