Baisley Pond Park Track Reconstruction and Synthetic Turf Field and Sports Lighting Construction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the track and convert the natural turf field to synthetic turf and construct sports lighting at Baisley Pond Park.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

Project Timeline

Design

Assigned & Start Date: January 2024
Projected Completion Date: June 2025
Completion Date: July 2025 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Baisley Pond Park, Queens
N. Conduit Avenue, 150th Street, Rockaway Blvd. and Baisley Blvd. South
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project