Umma Park Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct Umma Park.

Project Notes

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2022
Projected Completion Date: December 2023
Completion Date: May 2024 (Design)

Procurement

Start Date: May 2024
Projected Completion Date: April 2026
Adjusted Completion Date: February 2026 (Procurement)

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council

Location

Umma Park, Brooklyn
Ocean Avenue at Woodruff Avenue
Community Board: 14

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project