St. Vartan Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the playground in St. Vartan Park.

Project Notes

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2020
Projected Completion Date: February 2021
Completion Date: April 2023 (Design)

Procurement

Start Date: April 2023
Projected Completion Date: March 2026

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • City Council
  • Mayoral

Location

St. Vartan Park, Manhattan
1st Avenue between East 35th Street and East 36th Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project