St. Vartan Park Playground Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the playground in St. Vartan Park.
Project Notes
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2020
Projected Completion Date:
February 2021
Completion Date:
April 2023
(Design)
Procurement
Start Date: April 2023
Projected Completion Date:
March 2026
Adjusted Completion
Date:
February 2026
(Procurement)
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
St. Vartan Park, Manhattan
1st Avenue between East 35th Street and East 36th Street
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project