Galileo Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Galileo Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2024
Completion Date: April 2024 (Design)

Procurement

Start Date: April 2024
Projected Completion Date: May 2025
Completion Date: July 2025 (Procurement)

Construction

Start Date: September 2025
Projected Completion Date: September 2026

Understand how we build parks.

Funding

Total Funding: $7,096,000
Funding Sources:
  • City Council
  • Mayoral

Location

Galileo Playground, Bronx
Macombs Road between West 175th Street, West 176th Street
Community Board: 05

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project