East River Esplanade Stabilization and Reconstruction Phase 2
-
100% complete
-
100% complete
-
3% complete
This project will stabilize and reconstruct portions of the East River Esplanade.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
March 2020
Completion Date:
June 2022
(Design)
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
August 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
August 2027
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
East River Esplanade, Manhattan
East River Esplanade between East 96th Street and East 125th Street
Community Board: 08, 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project