East River Esplanade Stabilization and Reconstruction Phase 3

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will stabilize and reconstruct portions of the East River Esplanade.

Project Notes

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: July 2020
Completion Date: October 2024 (Design)

Procurement

Start Date: June 2022
Projected Completion Date: March 2026
Adjusted Completion Date: July 2025 (Procurement)

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million