Freshkills South Park Synthetic Turf Fields and Landscape Construction
-
100% complete
-
5% complete
-
0% complete
This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands at Freshkills South Park.
Project Notes
Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
December 2019
Completion Date:
March 2024
(Design)
Procurement
Start Date: August 2025
Projected Completion Date:
August 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Freshkills Park, Staten Island
Arthur Kill Road at Muldoon Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks about this project