Freshkills South Park Public Restroom Construction
-
100% complete
-
40% complete
-
0% complete
This project will construct a public restroom at Freshkills South Park.
Project Notes
Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
December 2019
Completion Date:
March 2024
(Design)
Procurement
Start Date: May 2024
Projected Completion Date:
May 2025
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Freshkills Park, Staten Island
Arthur Kill Road at Muldoon Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey