West 186th Street Basketball Court Reconstruction
-
100% complete
-
100% complete
-
1% complete
This project will reconstruct West 186th Street Basketball Court.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
June 2023
Completion Date:
December 2023
(Design)
Procurement
Start Date: December 2023
Projected Completion Date:
December 2024
Completion
Date:
February 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
August 2026
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
West 186th Street Basketball Court, Manhattan
West 186th Street between Audubon and St. Nicholas Avenues
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project