Court Square Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will reconstruct Court Square Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: September 2022 (Design)

Procurement

Start Date: September 2022
Projected Completion Date: May 2023
Completion Date: October 2024 (Procurement)

Construction

Start Date: February 2025
Projected Completion Date: February 2026

Understand how we build parks.

Funding

Total Funding: $3,999,000
Funding Source: Mayoral

Location

Court Square Park, Queens
Jackson Avenue, Court Square West, Thomson Avenue
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower