Flushing Meadows Corona Park Aquatic Center Ice Rink Chiller Plant Replacement

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will replace the chiller plant for the ice skating rink at Flushing Meadows Corona Park Aquatic Center.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2023
Projected Completion Date: October 2023
Completion Date: July 2025 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
131-04 Meridian Road
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project