Riverside Park Drainage System Reconstruction From 108th to 116th Street

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the drainage system at Riverside Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2021
Projected Completion Date: December 2022
Completion Date: December 2023 (Design)

Procurement

Start Date: December 2023
Projected Completion Date: December 2024
Completion Date: October 2025 (Procurement)

Construction

Start Date: October 2025
Projected Completion Date: April 2027

Understand how we build parks.

Funding

Total Funding: $25,964,000
Funding Source: Mayoral

Location

Riverside Park, Manhattan
Riverside Park from 108th to 116th Street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project