Riverside Park Drainage System Reconstruction From 108th to 116th Street
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the drainage system at Riverside Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
December 2022
Completion Date:
December 2023
(Design)
Procurement
Start Date: December 2023
Projected Completion Date:
December 2024
Completion
Date:
October 2025
(Procurement)
Construction
Start Date: October 2025
Projected Completion Date:
April 2027
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Riverside Park, Manhattan
Riverside Park from 108th to 116th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project