Riverside Park Drainage System Reconstruction From 108th to 116th Street

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the drainage system at Riverside Park.

Project Notes

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2021
Projected Completion Date: December 2022
Completion Date: December 2023 (Design)

Procurement

Start Date: December 2023
Projected Completion Date: December 2024
Adjusted Completion Date: September 2025 (Procurement)

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Riverside Park, Manhattan
Riverside Park from 108th to 116th Street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project