Michaelis-Bayswater Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
0% complete
This project will construct a public restroom building in Michaelis-Bayswater Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
April 2020
Completion Date:
March 2022
(Design)
Procurement
Start Date: March 2022
Projected Completion Date:
December 2022
Completion
Date:
September 2025
(Procurement)
Construction
Start Date: November 2025
Projected Completion Date:
April 2027
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Bayswater Park, Queens
Beach Channel Drive and Bay 32nd Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project