Kimlau Square Arch Reconstruction
-
100% complete
-
100% complete
-
2% complete
This project will reconstruct the arch in Kimlau Square.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
August 2022
Completion Date:
September 2022
(Design)
Procurement
Start Date: September 2022
Projected Completion Date:
June 2023
Completion
Date:
May 2025
(Procurement)
Construction
Start Date: July 2025
Projected Completion Date:
July 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Kimlau Square, Manhattan
Chatham Sq., Oliver St. and East Broadway
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project