Josephine Caminiti Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct Josephine Caminiti Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2022
Projected Completion Date: June 2023
Completion Date: July 2023 (Design)

Procurement

Start Date: July 2023
Projected Completion Date: July 2024
Completion Date: May 2025 (Procurement)

Construction

Start Date: July 2025
Projected Completion Date: July 2026

Understand how we build parks.

Funding

Total Funding: $4,282,000
Funding Source: City Council

Location

Josephine Caminiti Playground, Queens
102nd Street between Corona Avenue and Alstyne Avenue
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project