Josephine Caminiti Playground Reconstruction
-
100% complete
-
100% complete
-
6% complete
This project will reconstruct Josephine Caminiti Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2022
Projected Completion Date:
June 2023
Completion Date:
July 2023
(Design)
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
May 2025
(Procurement)
Construction
Start Date: July 2025
Projected Completion Date:
July 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Josephine Caminiti Playground, Queens
102nd Street between Corona Avenue and Alstyne Avenue
Community Board: 04
Project Staff
Project Liaison: Meira Berkower