South Rochdale Playground Reconstruction
-
100% complete
-
100% complete
-
36% complete
This project will reconstruct the basketball courts, multipurpose play area, and children's play area at South Rochdale Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
September 2023
Completion Date:
February 2024
(Design)
Procurement
Start Date: February 2024
Projected Completion Date:
February 2025
Completion
Date:
April 2025
(Procurement)
Construction
Start Date: June 2025
Projected Completion Date:
June 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
South Rochdale Playground, Queens
134th Road and 173rd Street
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project