Bleecker Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    11% complete

This project will reconstruct Bleecker Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: May 2023 (Design)

Procurement

Start Date: May 2023
Projected Completion Date: May 2024
Completion Date: June 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $2,299,000
Funding Source: City Council

Location

Bleecker Playground, Manhattan
Bleecker, Hudson, and West 11th Streets
Community Board: 02

 

Project Staff

Project Liaison: Steve Simon