Penn South Playground Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct Penn South Playground.
Project Notes
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
June 2024
Completion Date:
June 2024
(Design)
Procurement
Start Date: June 2024
Projected Completion Date:
March 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Penn South Playground, Manhattan
West 26th Street between 8th and 9th Avenues
Community Board: 04
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project