Penn South Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Penn South Playground.

Project Notes

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: June 2024 (Design)

Procurement

Start Date: June 2024
Projected Completion Date: March 2026

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Penn South Playground, Manhattan
West 26th Street between 8th and 9th Avenues
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project