Greencroft Playground Reconstruction
-
100% complete
-
100% complete
-
2% complete
This project will reconstruct the playground area at Greencroft Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2021
Projected Completion Date:
November 2022
Completion Date:
September 2023
(Design)
Procurement
Start Date: September 2023
Projected Completion Date:
September 2024
Completion
Date:
April 2020
(Procurement)
Construction
Start Date: June 2025
Projected Completion Date:
June 2026
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Greencroft Playground, Staten Island
Redgrave Avenue and Greencroft Avenue
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey