Greencroft Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct the playground area at Greencroft Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: November 2022
Completion Date: September 2023 (Design)

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Completion Date: April 2020 (Procurement)

Construction

Start Date: June 2025
Projected Completion Date: June 2026

Understand how we build parks.

Funding

Total Funding: $8,400,000
Funding Sources:
  • City Council
  • Mayoral

Location

Greencroft Playground, Staten Island
Redgrave Avenue and Greencroft Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project