Lafayette Gardens Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the playground at Lafayette Gardens.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: March 2023 (Design)

Procurement

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: September 2025 (Procurement)

Construction

Start Date: October 2025
Projected Completion Date: October 2026

Understand how we build parks.

Funding

Total Funding: $3,500,000
Funding Source: City Council

Location

Lafayette Gardens Playground, Brooklyn
Lafayette Avenue & Franklin Avenue
Community Board: 03

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project